You are currently leading an independent test team. Based on the information given in the scenario, identify how the team could be improved most effectively.
You are a test manager developing a master test plan. As part of the master test plan, you are defining exit criteria for the various test levels.
Which of the following exit criteria would be most appropriate and SMART for component testing, and which one would be most appropriate and SMART for system testing?
i. 95% of the tests prepared are executed successfully
ii. All test cases have been run
iii. 80% decision coverage for all tests run
iv. At least 30 defects have been found
v. At least two weeks of test execution
vi. No more open defects
You have recently been employed as a test manager for a software company producing Human Resource (HR) systems… You have been asked to write a test strategy for the project and have chosen to implement a flexible and change-relatedreactive test strategy.
Which of the following would be an essential part of your test approach?
Assume that you have calculated the following costs of quality:
Average cost of detection: €350
Average cost of internal failure: €250
Average cost of external failure: €4,500
The average costs of detection and internal failure are calculated using the number of defects found prior to release, while the average cost of external failure is calculated using the number of defects found after release.
What is the saving in cost of quality for each defect found in testing?