Test Manager ISTQB Certified Tester Advanced Level - Test Management v3.0

ISTQB Certified Tester Advanced Level - Test Management v3.0

Last Update Jun 29, 2026
Total Questions : 51

To help you prepare for the TM3 BCS exam, we are offering free TM3 BCS exam questions. All you need to do is sign up, provide your details, and prepare with the free TM3 practice questions. Once you have done that, you will have access to the entire pool of ISTQB Certified Tester Advanced Level - Test Management v3.0 TM3 test questions which will help you better prepare for the exam. Additionally, you can also find a range of ISTQB Certified Tester Advanced Level - Test Management v3.0 resources online to help you better understand the topics covered on the exam, such as ISTQB Certified Tester Advanced Level - Test Management v3.0 TM3 video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic BCS TM3 exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.

Questions 2

In an Agile context, defects are often fixed without writing a formal defect report. However, there are some conditions where it is good practice to write a defect report, even in an Agile context.

When is a defect report typically not written in an Agile context?

Options:

A.  

A defect that is blocking other iteration activities and cannot be immediately solved

B.  

A defect that cannot be solved in the same iteration

C.  

A defect that must be resolved by or in co-operation with other teams

D.  

A defect that is found for a high-priority user story

Discussion 0
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena May 28, 2026
Great. Yes they are really effective
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson May 15, 2026
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie May 2, 2026
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh May 4, 2026
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Questions 3

Which of the following is not true regarding applying a model-based approach, e.g., TMMi, for improvements at project level?

Options:

A.  

The assessment should include test management processes such as test planning and test monitoring and control

B.  

The assessment should include test engineering processes such as test design, test implementation and test execution

C.  

The assessment should include areas such as test policy and test organisation

D.  

Practices at organisational level should be tailored appropriate to the project's context

Discussion 0
Questions 4

Three exit criteria have been defined for a project:

Options:

A.  

Test cases passed is more than 70%

B.  

Number of outstanding defects is less than 5

C.  

Number of defects per test case is less than 0.5 The first week of the testing has shown the following results (Mon–Fri):Defects Found = 21 (3+4+2+5+7)Defects Fixed = 8 (0+2+2+3+1)Tests Run = 43 (10+3+20+5+5)Tests Passed = 24 (5+3+15+0+1)

D.  

Criteria A = OK, criteria B = OK, criteria C = OK

E.  

Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK

F.  

Criteria A = OK, criteria B = NOT OK, criteria C = NOT OK

G.  

Criteria A = NOT OK, criteria B = NOT OK, criteria C = NOT OK

Discussion 0
Questions 5

Factors that are important to take into account when performing test estimation include:

i. The quality of the test basis

ii. The availability of test automation

iii. The amount of rework required

iv. The distribution of testing across several locations

The various factors can be grouped by characteristic. Examples of characteristics include:

Options:

A.  

Test context

B.  

Test results

C.  

Product

D.  

Development processWhich factor is related to which characteristic?

E.  

A = i, B = ii, C = iii, D = iv

F.  

A = iv, B = iii, C = i, D = ii

G.  

A = iv, B = iii, C = ii, D = i

Discussion 0