Question 16

The Cycle Time metric for a certain Work Item cannot be used:

(choose the best two answers)

Options:

A.

As a leading indicator to the length of the feedback loop for that Work Item.

B.

To help the Scrum Team inspect and adapt their process.

C.

As a lagging indicator to the length of the feedback loop for that Work Item.

D.

To help the Developers inspect and adapt their Sprint in the Daily Scrum.

E.

To influence the team's SLE.

Discussion
Question 17

When the Developers limit Work in Progress (WIP) inside a Sprint, what would you expect to

observe?

(choose the best three answers)

Options:

A.

The Developers would stop beginning work, and instead, start finishing work.

B.

The amount of work done by the end of the Sprint would be reduced.

C.

Self-management would be strengthened as a result of increased transparency.

D.

Increased collaboration/swarming between the Developers.

Discussion
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik May 10, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie May 26, 2026
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris May 26, 2026
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan May 26, 2026
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella May 2, 2026
That's great. I think I'll give Cramkey Dumps a try.
Question 18

What is Kanban?

(choose the best answer)

Options:

A.

A methodology aimed at visualizing your Workflow for effectiveness and enhance

productivity within the team.

B.

A strategy for optimizing the flow of value through a process that uses a visual, Work

in Progress (WIP) limited pull system.

C.

A set of practices that are additive to the Scrum framework.

D.

None of the above.

Discussion
Question 19

Scrum Teams using Kanban can start to increase predictability by:

(choose the best answer)

Options:

A.

Visualizing the Workflow using a Kanban board.

B.

Improving transparency by having a CFD, Control Chart and Aging chart.

C.

Inspecting and adapting the Product Backlog during the Sprint Review.

D.

Reducing the amount of work in progress by introducing Work in Progress (WIP)

Limits.