Question 12

As a Scrum Master, you must be familiar with the Risk Assessment Techniques that are used to assess the likelihood and impact of risks on a project. Select the inappropriate Risk Assessment Technique pairing with its salient qualities.

Options:

A.

Expected Monetary Value: Product of monetary impact and risk's probability.

B.

Pareto Analysis: Ranks risks by magnitude.

C.

Probability Impact Grid: Values of potential events are used to calculate the overall impact of risk occurrence.

D.

Probability Trees: A branch for each possible outcome of potential events is represented on a graph.

Discussion
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Oct 19, 2026
That sounds really useful. I'll definitely check it out.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Oct 10, 2026
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Oct 12, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Andrew
Are these dumps helpful?
Jeremiah Oct 12, 2026
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Oct 11, 2026
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Question 13

The Product Owner on a project to manufacture components for engines used in submarines received feedback from the customer after the first release that there were some defects in the product, but that the product could be released despite the defects. However, if there is an increase in the number of defects, the deliverables would be rejected. This is an example of:

Options:

A.

Risk Tolerance

B.

Risk Seeking

C.

Risk Appetite

D.

Risk Threshold

Discussion
Question 14

In a Scrum project, which of the following is NOT a responsibility of a Scrum Master?

Options:

A.

Groom the Prioritized Product Backlog.

B.

Coordinate creation of the Release Planning Schedule.

C.

Facilitate Prioritized Product Backlog Review Meetings.

D.

Represent the Scrum Core Team to provide lessons from the project.

Discussion
Question 15

Which of the following statements about Scrum's history is INCORRECT?

Options:

A.

The idea of Scrum was derived from a “rugby” approach in which a team tries to go the distance as a unit, passing the ball back and forth.

B.

Takeuchi and Nonaka proposed that product development should be like a sequential relay race.

C.

Scrum was based on a flexible and all-inclusive product development strategy where the development team works as a unit to reach a common goal.

D.

Takeuchi and Nonaka based their approach on manufacturing case studies from various industries.

Discussion