SAP E_ACTCLD_21 Exam Overview :

Exam Name: SAP Certified Specialist - SAP Activate for Cloud Solutions Project Manager
Exam Code: E_ACTCLD_21 Dumps
Vendor: SAP Certification: SAP Certified Specialist
Questions: 167 Q&A's Shared By: samson
Question 24

What is the purpose of the Solution Validation activity in the Explore phase? There are 3 answers to this question.

Options:

A.

To identify gaps

B.

To log additional scope items

C.

To verify technical installation

D.

To challenge changes to standard

E.

To educate project participants

Discussion
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Dec 5, 2025
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Dec 28, 2025
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Dec 3, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Dec 19, 2025
Great. Yes they are really effective
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Dec 9, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Question 25

What are the responsibilities of the Project Team on level 4 in the picture below? There are 2 answers to this question.

Options:

A.

Set Project policy, standards and oversight

B.

Identify and resolve issues and risks

C.

Perform status reporting and communication

D.

Set business priorities, goals and objectives

Discussion
Page: 6 / 6

E_ACTCLD_21
PDF

$36.75  $104.99

E_ACTCLD_21 Testing Engine

$43.75  $124.99

E_ACTCLD_21 PDF + Testing Engine

$57.75  $164.99