Question 24

Giving or taking a payment of money to induce a person to act in breach of trust and do something they should not do is called:

Options:

A.

Embezzlement

B.

Extortion

C.

Fraud

D.

Bribery

Discussion
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Oct 17, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Oct 15, 2025
That's great. I think I'll give Cramkey Dumps a try.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Oct 17, 2025
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Oct 16, 2025
Great. Yes they are really effective
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Oct 16, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Question 25

Which of the following is not a concept related to quality management?

Options:

A.

SPC

B.

FMEA

C.

TQM

D.

SPQR

Discussion
Question 26

Spot the odd one out.

Options:

A.

Effectiveness

B.

Ecology

C.

Efficiency

D.

Economy

Discussion
Question 27

It is thought that the cause of a negative variance in the materials budget is the poor negotiation skills of procurement staff. Which of the following (select two) would be a move in the right direc-tion to remedy this situation?

Options:

A.

Replace the Head of Procurement

B.

Use competition to find suppliers with lower prices

C.

Provide effective negotiation training for procurement staff

D.

Increase stockholding of the materials in QUESTION NO: to ensure supply

Discussion