Question 8

According to Hofstede's Cultural Dimensions, Individualism is when a person prioritises themselves over a group. Is this correct?

Options:

A.

yes – individualism is seen as a selfish culture

B.

yes – this is the opposite of collectivism

C.

no – this is where an individual does not take risks that may have an adverse affect on themselves

D.

no – individualism means accepting immediate gratification

Discussion
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Oct 24, 2025
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 1, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Nell
Are these dumps reliable?
Ernie Oct 21, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Oct 25, 2025
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Question 9

Skipped

An End-Of-Project Review may include the hiring of an external consultant to audit a project. This is particularly true in the Public Sector and for high-value/high-risk projects. The Auditor is likely to review the project's performance against what?

Options:

A.

Other similar projects completed by the organization

B.

Projects completed in the private sector

C.

The project plan

D.

Configuration management

Discussion
Question 10

Which project management methodology outlines a process for closing a project?

Answer Options:

Options:

A.

Monte Carlo

B.

Critical Path

C.

MRP

D.

Prince2

Discussion
Question 11

Scenario (same as Question 16):

    Which type of contract would be the most suitable for working with the new client?

Options:

A.

JCT

B.

FIDIC

C.

IMechE

D.

NEC

Discussion