Black Friday VIP Weekend - 75% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 75brite

CIPS Updated L6M8 Exam Questions and Answers by ivie

Page: 5 / 8

CIPS L6M8 Exam Overview :

Exam Name: Innovation in Procurement and Supply
Exam Code: L6M8 Dumps
Vendor: CIPS Certification: CIPS Level 6 Professional Diploma in Procurement and Supply
Questions: 120 Q&A's Shared By: ivie
Question 20

Below are details of 5 companies who are all embarking on the launch of a new product. For each company, you must decide which innovation tactic they are using and the priority for the new contract.

Company 1: The company aims to design the specification around customers’ requirements. They are keen to ensure a balance between costs and the service provided.

Company 2: This company attends regular conferences held by a professional body and will use the information discussed to inform upon the specification. They are keen to ensure sufficient interest from the marketplace so are placing a priority on networking at the conferences.

Company 3: There is a small group of internal stakeholders who meet regularly at Company 3 who discuss supply chain and organisational integration. The priority for the group is to ensure that the supplier of the new product’s raw materials meets the company’s standards for environmental protection.

Company 4: This company has regular phone calls with suppliers discussing ideas for the new product. Once the product is launched, the focus will be on ensuring that the supplier is held to account.

Company 5: Equipment has been loaned to a supplier to produce a prototype of the new product. The aim of the project is to ensure the supplier is capable of producing the components required for the product before the contract is signed.

Complete the table below by listing the innovation tactic and contract priority for each company; focus group, innovation council, technology transfer, collaboration, supplier forum, early supplier involvement, supplier development, balanced scorecard, contract management, selection, value for money, bidding.

Which of the following will you put into box 7?

Options:

A.

supplier development

B.

balanced scorecard

C.

contract management

D.

selection

E.

value for money

F.

bidding

Discussion
Question 21

What are the defining characteristics of ' Big Data ' ? Select THREE

Options:

A.

viability

B.

volume

C.

variety

D.

validity

E.

velocity

Discussion
Question 22

What are the benefits of early supplier involvement? Select all that apply.

Options:

A.

information sharing

B.

higher levels of innovation

C.

better environmental protection

D.

smaller supply chains

Discussion
Question 23

A piece of computer software runs an analysis about possible disaster scenarios such as a power failure to the manufacturing plant, and tells an organisation how best to react in the situation. What type of analytics does this software provide?

Options:

A.

descriptive

B.

prescriptive

C.

predictive

D.

diagnostic

Discussion
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Oct 26, 2026
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Oct 7, 2026
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Oct 13, 2026
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Oct 16, 2026
Good point. Thanks for the advice. I'll definitely keep that in mind.
Page: 5 / 8

L6M8
PDF

$27.5  $109.99

L6M8 Testing Engine

$32.5  $129.99

L6M8 PDF + Testing Engine

$42.5  $169.99