According to Section 6.6 of API 580 (2016), titled “Estimating Resources and Time Required,” it is clearly stated:
“The resources and time required to implement an RBI assessment will vary widely between organizations depending on a number of factors including the following:
a) implementation strategy/plans.
b) knowledge and training of implementers.
c) availability and quality of necessary data and information.
d) availability and cost of resources needed for implementation.
e) amount of equipment included in each level of RBI analysis.
f) degree of complexity of RBI analysis selected.
g) degree of precision required.”
This confirms the following are among the officially listed influencing factors:
A. Knowledge and training of implementers✔
C. The degree of precision required✔
D. Amount of equipment included✔
However:
B. Cost of mitigation activities —✘Not listed in Section 6.6 as a driver for time/resources during implementation.
E. Type of damage mechanisms involved —✘Relevant to PoF modeling, but not a direct listed factor for estimating time/resources needed to implement the RBI.
[Reference: API 580, 2nd Edition (2016), Section 6.6 – Estimating Resources and Time Required, , , ]