Question 16

A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.

Which action should the stakeholder take to log the risk?

Options:

A.

Log a risk as part of the project business case and identify it as a "schedule" risk.

B.

Log an issue on the project and explain that the completion date is at risk.

C.

Create a task in the project and set the Planned Completion Date for 2 weeks.

Discussion
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Oct 23, 2025
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Oct 5, 2025
That's great to hear. I am going to try them soon.
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Oct 15, 2025
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Oct 3, 2025
did you use PDF or Engine? Which one is most useful?
Question 17

A project manager wants to see all of the assignees for each task in a project.

Which field should the manager reference to view all task assignees?

Options:

A.

Assigned To

B.

Assignments

C.

Assigned

Discussion
Question 18

A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.

How should the project manager keep these team members apprised of updates?

Options:

A.

Subscribe the team members to the request.

B.

Ask the team members to add the request to their favorites.

C.

Make the team members all primary contacts on the request.

Discussion
Question 19

A project manager is assigned to a new Workfront request. The request specifies that themanagement team’s sign-off is needed before the project can begin.

What is the appropriate action for the project manager to take?

Options:

A.

Convert the issue into a project using a project template.

B.

Email the management team and request their approval.

C.

Use a customized approval process to route the issue for approval.

Discussion