To help you prepare for the C_TS412_2021 SAP exam, we are offering free C_TS412_2021 SAP exam questions. All you need to do is sign up, provide your details, and prepare with the free C_TS412_2021 practice questions. Once you have done that, you will have access to the entire pool of SAP Certified Application Associate - SAP S/4HANA Project Systems C_TS412_2021 test questions which will help you better prepare for the exam. Additionally, you can also find a range of SAP Certified Application Associate - SAP S/4HANA Project Systems resources online to help you better understand the topics covered on the exam, such as SAP Certified Application Associate - SAP S/4HANA Project Systems C_TS412_2021 video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic SAP C_TS412_2021 exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.

Questions 2

An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

Options:

A.  

The network profile

B.  

The control key

C.  

The table of MRP controllers

D.  

The scheduling parameters for the network

Discussion 0
Questions 3

You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation.,

and have entered the quotation ...

What is the typical sequence for the following business transactions and document.

Options:

A.  

Benefic check - Acceptance of performed service- vendor selection - purchase order handing- purchase order monitoring-Good receipt - invoce ..

B.  

Vendor selection - purchase order handing- purchase order monitoring- Benefic Check- Acceptance of performed services.

C.  

Vendor selection - purchase order handing - invoice receipt - purchase order monitoring -Good receipt.

D.  

Vendor selection- Purchase order handing-purchase order monitoring-Good receipt- Invoice receipt.

Discussion 0
Questions 4

Which statement regarding the creation of a new work breakdown structure (WBS element) are true?

Note : there are 3 correct answer for this question.

Options:

A.  

You can create several WBS elements per level.

B.  

A new work breakdown structure must contain up to 10 levels.

C.  

A WBS element of the new project can be assigned to a different project definition.

D.  

WBS element can be a planning element, an account assignment element, and a billing element at the same time.

E.  

The WBS structure can contain several level 1 WBS element,

Discussion 0
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Sep 22, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Sep 1, 2025
YES….. I saw the same questions in the exam.
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Sep 7, 2025
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Sep 16, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Questions 5

Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.

What benefit do they have when using delivery from project (CNSO).

Options:

A.  

With delivery from projects You can generate goods issues for project without creating delivery documents.

B.  

With delivery from projects good receipt are automatically posted while saving.

C.  

With delivery from projects you can generate purchase requisitions for sub-contractors.

D.  

With the delivery from project you can deliver material component assigned to your network.

Discussion 0

C_TS412_2021
PDF

$36.75  $104.99

C_TS412_2021 Testing Engine

$43.75  $124.99

C_TS412_2021 PDF + Testing Engine

$57.75  $164.99