Question 8

Which collaboration features can SAP jam users access in the SAP methodology Jam group?

There are 2 correct answers to this question.

Options:

A.

Comment on key deliverables

B.

Update key deliverables wikis

C.

Ask questions

D.

Tweet questions

Discussion
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Aug 14, 2024
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 22, 2024
They give you a competitive edge and help you prepare better.
Nia
Why are these Dumps so important for students these days?
Mary Oct 9, 2024
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Aug 8, 2024
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Question 9

Working in an Agile approach, what should your planning look like at the Beginning of the realize phase?

Options:

A.

Project scope and planning are completed and final

B.

User stories are in a ready state for NO more than the first three sprints

C.

Go-live scope is fixed on the first of January the following year

D.

Timelines of the sprint may differ due to the workload

Discussion
Question 10

Which value chains does SAP solution manager 7.2 deliver?

There are 3 correct answers to this question.

Options:

A.

Requirements-to-deploy

B.

Detect-to-correct

C.

Request-to-fulfil

D.

Hire-to-retire

E.

Cash-to-order

Discussion
Question 11

Which activity helps the Project Team add User Stories to the Product Backlog?

Options:

A.

Assessing project risks

B.

Preparing a project schedule

C.

Conducting the Solution Validation workshop

D.

Planning the User Acceptance Test

Discussion