Question 8

Where do you control whether a project stock is managed as valuated or non-valuated project stock?

Options:

A.

In the network activity

B.

In the project definition

C.

In the WBS element

D.

In the material master

Discussion
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Nov 19, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Nov 9, 2025
Yeah, definitely. I experienced the same.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Nov 10, 2025
That’s great!!! I’ll definitely give it a try. Thanks!!!
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Nov 18, 2025
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Question 9

Which organizational structures are required for network activities? Note: There are 3 correct answers to this question

Options:

A.

Controlling area

B.

Plant

C.

Sales organization

D.

Company code

E.

Operating concern

Discussion
Question 10

An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

Options:

A.

The network profile

B.

The control key

C.

The table of MRP controllers

D.

The scheduling parameters for the network

Discussion
Question 11

Cost and Budget

What function are available for period end-closing in the project System?

Options:

A.

Result analysis

B.

Progress analysis

C.

Milestone trend analysis

D.

Settl ement

E.

Confirmation

Discussion