SAP C_ACTIVATE22 Exam Overview :

Exam Name: SAP Certified Associate - SAP Activate Project Manager
Exam Code: C_ACTIVATE22 Dumps
Vendor: SAP Certification: SAP Certified Associate
Questions: 95 Q&A's Shared By: ovie
Question 8

For which of the following products do you find a specific set of best practices for the public sector?

Options:

A.

SAP S/4HANA

B.

SAP SuccessFactors Employee Central

C.

SAP Marketing Cloud

D.

SAP S/4HANA Cloud, public edition

Discussion
Andrew
Are these dumps helpful?
Jeremiah (not set)
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka (not set)
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Robin
Cramkey is highly recommended.
Jonah (not set)
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper (not set)
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Question 9

Which of the following activities take place during the Discover phase in an SAP BW/4HANA implementation?Note: There are 2 correct answers to this question.

Options:

A.

Create, review, and sign off the Create Project Management Plan.

B.

Discuss the Benefits of SAP Data Warehouse Cloud.

C.

Discuss the Benefits and Functionality of SAP Analytics Cloud

D.

Create, review, and sign off the Project Charter.

Discussion
Question 10

Which of the following steps are part of the fit-to-standard process? Note: There are 2 correct answers to this question.

Options:

A.

Design to-be business process models

B.

Review Best Practices process flow

C.

Document integration requirements

D.

Enable customers on standard business processes

Discussion
Question 11

When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?

Options:

A.

Realize phase scope, planning, and budget should be completed and final.

B.

Release plan and sprint ceremony guidelines should be finalized.

C.

Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.

D.

User stories on product backlog should be in ready state for the first 2 to 3 sprints.

Discussion